- out of step protection relay setting calculation,shahid mofatteh powerplant
- supervision of out of step protection relay setting calculation,bushehr nuclear powerplant
- protection substation relay setting calculation,bushehr nuclear powerplant
- perform the necessary test and check settings and provide the necessary computing for all protective relays of powerplants thermal units:
- Lowshan
- Montazar ghaem
- Kermanshah
- Neka
- Zahedan
- Gilan
- Gas company dedicated powerplant in Aghaar and Dallan
- Relays test for 20 gas units of Ray powerplant
- Relays test for steam units of Zargan powerplant
- Test and commmissioning of all protection relays for local power of Hamedan powerplant
- Protection Relays test for steam units of Tabriz powerplant
- Installation and commissioning of longitudinal differential relays of 400 kv line,between shahid rajaee combined cycle & steam powerplant
- Protection relays setting calculation for units & transformator of Parand,Montazar e ghaem,Semnan and Shahrood powerplant inorder to coordinating with OC/EF network
- Check Relays setting of Abadan & Besat powerplant
- Protection relays setting calculation for shahid Rajaee powerplant
- Case study about some protection relays setting such as: Loss of field,Reverse power, Negative sequence, Stator Earth Fault,Voltage, Out of step, Under Excitation
Automation and Data Acquisition References:
- Engineering services and supervision of erection and commissioning of ABB terminals in 19 post transfer
- Sub transmission substation, dispatching related requirements, execution procedures preparation services
- Supervision and consultant of Mosalla sub transmission dispatching center installation and commissioning
- Replacing Main and UIOC cards with 14 CPU card Designed, produced and installed for MN2000 terminals
- Consultant for sub transmission substations data gathering and preparing signal lists groups
- Consulting and supervision services for installation and commissioning of Qom sub transmission substation dispatching connection to Sa’adat Abad Center
- Design, Production and, installation and commissioning of IEC-6870-5-101nconverter to DNP3 in Tehran’s north west dispatching center
- ABB Terminal Connection to Ahwaz Sub transmission dispatching center
- Hitachi to IEC 60870-5-101 converter for Ahwaz DCS 1
- Installation of Fault recorder system for Shahid Montazeri power plant
- HMI system installation for Ramin 1&2 power plant’s substation
- Consultant and supervisor for Tehran sub transmission centers (4 centers)
- Consultant and supervisor for Qom dispatching center
- Standardization of Tehran sub transmission centers protocol
- Consultant for connection of Tehran sub transmission centers to DCS
- Production and installation of 30 RTU system for Tehran sub transmission center
- Connecting Sardar-Jangal substation DCS (SIEMENS SAT) to Mosalla dispatching center
- Connecting Shahriar substation DCS (SIEMENS SICAMPAS) to Tehran transmission dispatching centerConnecting Fars Substations DCSs to Shiraz transmission and sub transmission control centers
- Installation and commissioning of HMI system for Khuzestan transmission substations
- Commissioning of Ahwaz sub transmission control center using IEC 60870-5-104 protocol
- Consultant for relocation of new Tehran AOC control center using multi variable decision models
- Execution of telemetry system for expansion of 230/400 substation of Zanjan-Soltaniyeh power plant
- Caspian 63KV substation telemetry system
- Zin Abad 63KV substation telemetry system
- Interfacing project of Zarin Abad 63KV substation
- Hirbod 63KV substation telemetry and telecommunication systems
- Khales Sazan dedicated 63/20 substation telemetry system
- Installation and commissioning of PMS for air unit of Fajr Petrochemical extension project
- Providing substation measurement systems to be installed in Hormozgan Regional Electric Co.
- Mehregan 63KV substation telemetry and telecommunication system
- Dedicated 63KV Gheytool substation and expansion of Soltan Abad substation telemetry and telecommunication system
- PMS/PDCS of Fajr#2 petrochemical plant fiber optic connection to Arvand petrochemical plant
- Installation and commissioning of Shiraz consumable water treatment control center
- Installation and commissioning of Bandar-Lengeh ( Kong) 230KV substation DCS system
- Procurement, installation and commissioning of Mahshahr gas export port 132KV substation control and telecommunication system
- Procurement, and commissioning of Minab 230KV substation communication PLC system and also 10 communication link
- Design, procurement, installation and commissioning of automation interface (SCADA/HMI) of Roodan 230KV substation (based on ABB product)
- Design, procurement, installation and commissioning of automation interface (SCADA/HMI), RTU, power supply, ABB and connecting to control center
- Telemetry system, RTU and radio link for wells and reservoir of Varzaghan water transmission system (based on SIEMENS and Citect)
- Design, procurement, installation and commissioning of automation interface (SCADA/HMI), RTU, power supply, connecting to control center of Jenah 63KV substation expansion (based on ABB)
- Design, procurement, installation and commissioning of automation interface (SCADA/HMI), RTU, power supply, connecting to control center of Ghazvin 63KV substation expansion (based on Infoware RTU)
- Suply Instrumentation,(Orifice Plate, Flange and Transmitters)- EMERSON
- Design, supply, installation interface, RTU, power supplies, telecommunications equipment and transmission of 63 kV Buin Zahra- IDS
- Design, procurement, installation and commissioning of automation interface (SCADA/HMI), RTU, power supply, connecting to control center of Ghazvin 63KV substation expansion (based on Infoware RTU)
- Power supply and fiber optic connection of Hormozgan substations (based on CISCO product)
- Installation and commissioning of 95 no. of ACTARIS SL7000 meters
- Design, procurement and execution of telemetry system of Hormozgan Steel Company